The project will construct 26 Gas Wells in Haradh and Hawiyah Areas. RTU Data and voice Communication requirements will be provided by Installing the SIEMENS OPEN TRANSPPORT DUAL RING NETWORK. These Gas Wells will be interconnected via Fiber Optic Transmission System (FOTS). Communication work covers the installation of fiber optic backbone cable (12 strands, non-zero dispersion shifted) from Gas Wells, Remote Headers and Gas Manifolds as OTN nodes that compose the FOTS (fiber optic transmission system) in Haradh and Hawiyah areas. |
Communication |
Saudi Aramco |
The project will upgrade the AL-KHAFJI KGOC/AGOC Offshore Gas Wells control systems for Flow Stations namely Y-1, Y-2, Y-3, Y-4 and at Gathering Stations in the Offshore Control Platform (OCP). Communications network for the control system will be provided by installing new fiber optic cable and splicing to the existing composite submarine cable. |
Communication |
Khafji Joint Operations (KJO) |
The project will provide communication services for approximately 400 people at Hawiyah NGL Recovery Plant (HNRP). The project encompasses the design, Installation, Construction, Configuration, Testing and Commissioning of Permanent Communication of Permanent Communication Facilities. As part of the project, Hawiyah NGL Recovery Plant will be linked to existing Saudi Aramco Corporate Network via Hawiyah Gas Plant and Uthmaniyah Gas Plant existing Communication Facilities using the highly reliable Fiber Optic Cable. |
Communication |
General Dynamics Saudi Arabia Ltd. (GD) |
The project will provide communication services for approximately 400 people at Hawiyah NGL Recovery Plant (HNRP). The project encompasses the design, Installation, Construction, Configuration, Testing and Commissioning of Permanent Communication facilities. As part of the project, Hawiyah NGL Recovery Plant will be linked to existing Saudi Aramco Corporate Network via Hawiyah Gas Plant and Uthmaniyah Gas Plant existing Communication Facilities using the highly reliable Fiber Optic Cable. |
Communication |
Dyn Al-Rushaid |
Replace the obsolete Control Systems and unsafe Control Buildings at Uthmaniyah GOSP 7, 8 and 10 with new Control Systems in new SSD compliant blast resistant Control Buildings to minimize unscheduled downtime and provide safe operating environments. |
Communication |
BI-8261, Utmaniyah GOSPS 7, 8 and 10 Control Systems Upgrade |
EPC Contract for the engineering, procurement, construction and testing of a nominal 250MW power and 510 t/h steam co-generation facility. |
Communication |
Sales Gas Piping & Metering Co-Generation Plant |
Provide detailed design packages for Electrical and Communication requirements of the GOSPs Upgrade Project. |
Communication |
BI-8259, Control System Upgrade AINDAR GOSPs 1 & 3 |
Project Management, Engineering, Procurement, Construction Management and Technical Support for Refinery Control System Upgrade Project, and Advance Control Implementation. |
Communication |
Yanbu Control Systems Upgrade |
Provision of a Vessel Traffic Management System (VTMS) at Ras Tanura Port consisting of an Integrated Computer System centrally located at a new Port Control Center (PCC) Building in Ras Tanura. The new system included radar sensors, mooring sensors, digital microwave link, networked computer system, VHF-DF surveillance, vessel approach monitoring, ship-board transponders and GPS, tidal sensors, interface equipment and fiber optic connectivity with existing communication facilities. |
Communication |
BI-8187, Vessel Traffic Management System (VTMS) at Ras Tanura Port |
Outside Plant and LAN engineering/design for the Dhahran intra-building transport facilities. Three (3) new buildings at the West Park Office Complex are to be connected. |
Communication |
BI-3340, West Park Office Complex Data Communications |